New building project 84339 Unterdietfurt near Eggenfelden (district Rottal-Inn):
In the last weeks we could successfully complete the earthworks for house 2 & start with the construction of the ground slab (construction phase 2).
Furthermore, the rough installations of house 4 were completed & all fire doors in the basement area were set. The work on the interior plastering will start in week 09.
In mid-March, the rough installations of house 3 will also be completed. Subsequently, the interior plastering work will be started directly there as well.