New building project 84339 Unterdietfurt near Eggenfelden (district Rottal-Inn):
In the last week we could concrete the basement ceiling of house 4 as well as the underground parking ceiling between house 3 & house 4. Parallel to this, the basement partition walls in house 4 were bricked. After completion of the basement slab of house 4, the masonry work of the first floor was started.
Furthermore, the earthworks for the underground car park to house 2 were completed (start of construction phase 2 - construction of house 2 as well as house 1). The extension of the underground car park is progressing step by step.